Design Aspects
•Construct an 80' River access channel for ocean going barges
•Construction two Pre-Engineered Metal Buildings for assembly buildings
•Develop the Site to meet Putnam County DRC requirements.
•Accommodate three existing structures, and two new Structures, new paving, loading & unloading areas and expanded site utilities
•Coordinate Civil, Structural, and Environmental Engineers to produce FDEP Applications as needed for approval
•Coordinate with Surveyor, Bathymetric Surveyor, and Hydro logic Analysis.
•Seek/Obtain permits for construction from FDEP, USFWS, Corps of Engineers, and SJRWMD, as well as Putnam County.

|